Other than cash, a standby letter of credit (LoC) is generally considered the most liquid form of performance security. While beneficiaries generally believe drawing on an LoC should be a relatively simple process, many do not understand the extent to which the counterparty could try to stop you. This issue was addressed in Pacific Atlantic Pipeline Construction v Coastal Gaslink Pipeline Ltd (2023) ABKB 736.
In this case, Coastal Gaslink Ltd. (CGL) contracted with Pacific Atlantic Pipeline Construction Ltd. (PAPC) to construct portions of the coastal gaslink pipeline project (Project). During the Project, disputes arose in connection with the performance of PAPC's work and CGL ultimately terminated the contract and arbitration proceedings were commenced.
In connection with the dispute, CGL sought to draw-down on an LoC provided by PAPC as contract security. However, PAPC applied to the Court for an interim injunction in an attempt to stop CGL from calling on the LoC until the conclusion of the arbitration process.
Despite there being no prerequisite conditions to calling on the letter of credit in the contract, PAPC made several arguments in support of their position that CGL should not be permitted to call on the LoC pending resolution of the arbitration. These arguments included:
a. CGL was required to use discretion when drawing on the LoC to ensure it aligned with the "purposes of the contract", where the purpose of the contract was paying for and completing construction work and the work had been substantially completed by the time CGL called on the letter of credit; and
b. CGL’s actual goal in drawing on the LoC was to gain leverage during the arbitration and not for a legitimate purpose.
Although not specifically identified by the Court, the three-part test to determine whether or not to grant an interim injunction includes: (1) is there a serious issue to be tried? (2) would the applicable suffer irreparable harm that cannot be compensated in damages if an injunction is not granted? and (3) does the balance of convenience favor granting an injunction?
Here, the Court noted that the PAPC must first prove a strong prima facie case that drawing on the LoC would violate a contractual obligation owed by CGL. For the following reasons, the Court concluded that PAPC failed to meet this requirement:
In conclusion, the Court confirmed that since LoCs are customary in many commercial arrangements, Courts should limit circumstances where an injunction can be used to stop a beneficiary from enforcing their rights. The Court also reiterated the necessity for a strong prima facie case to obtain an interim injunction and since the court found that PAPC was unable to demonstrate one, PAPC’s application was denied.
Interestingly, despite denying PAPC's application, and after the oral hearing of the application, the Court did grant an interim injunction until January 8, 2024, since the courts were closed over the holidays and to not otherwise impact PAPC's timely right to file an appeal. The justification for granting this interim injunction is unclear and may create some uncertainty regarding the enforcement of LoCs.
Although PAPC was ultimately unsuccessful in preventing CGL from drawing on the LoC, this decision reinforces that a party may still try to seek an injunction to prevent a beneficiary from drawing on an LoC—particularly when the merits of an underlying dispute have not been determined. However, in such circumstances, this decision confirms that: